PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 10 Topic 2 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 10 Topic 2 Discussion

PMI-100 Exam Topic 2 Question 10 Discussion:
Question #: 10
Topic #: 2

Which of the following are outputs of Develop Project Team?


A.

Human resources plan changes and project staff assignment updates


B.

Project management plan updates and enterprise environmental factor updates


C.

Resource calendars and project management plan updates


D.

Team performance assessments and enterprise environmental factor updates


Get Premium PMI-100 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.