PMI-100 Exam Topic 12 Question 115 Discussion:
Question #: 115
Topic #: 12

A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:


A.

Adaptive


B.

Predictive


C.

Incremental


D.

Iterative