PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 114 Topic 12 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 114 Topic 12 Discussion

PMI-100 Exam Topic 12 Question 114 Discussion:
Question #: 114
Topic #: 12

An output of the Create WBS process is:


A.

Scope baseline.


B.

Change requests.


C.

Accepted deliverables.


D.

Variance analysis.