PMI Project Management Professional v5 PMI-001 Question # 80 Topic 9 Discussion

PMI Project Management Professional v5 PMI-001 Question # 80 Topic 9 Discussion

PMI-001 Exam Topic 9 Question 80 Discussion:
Question #: 80
Topic #: 9

Which of the following investigates the likelihood that each specific risk will occur?


A.

Risk register


B.

Risk audits


C.

Risk urgency assessment


D.

Risk probability and impact assessment