PMI Project Management Professional v5 PMI-001 Question # 70 Topic 8 Discussion

PMI Project Management Professional v5 PMI-001 Question # 70 Topic 8 Discussion

PMI-001 Exam Topic 8 Question 70 Discussion:
Question #: 70
Topic #: 8

Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?


A.

Control Scope


B.

Collect Requirements


C.

Create WBS


D.

Define Scope


Get Premium PMI-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.