Question #: 59
Topic #: 6

For any given project, the project manager, in collaboration with the project team, is responsible for:


A.

Applying knowledge, skills, and processes uniformly.


B.

Informing the project sponsor about which processes are going to be used.


C.

Tailoring the processes to fit the abilities of the organization.


D.

Determining which particular processes are appropriate.