PMI Project Management Professional v5 PMI-001 Question # 39 Topic 4 Discussion

PMI Project Management Professional v5 PMI-001 Question # 39 Topic 4 Discussion

PMI-001 Exam Topic 4 Question 39 Discussion:
Question #: 39
Topic #: 4

Labor, materials, equipment, and supplies are examples of:


A.

Resource attributes.


B.

Resource types.


C.

Resource categories.


D.

Resource breakdown structures (RBS).