PMI-001 Exam Topic 4 Question 37 Discussion:
Question #: 37
Topic #: 4

Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?


A.

Analogous Estimating


B.

Expert Judgment


C.

Optimistic Estimates


D.

Reserve Analysis