PMI Project Management Professional v5 PMI-001 Question # 32 Topic 4 Discussion

PMI Project Management Professional v5 PMI-001 Question # 32 Topic 4 Discussion

PMI-001 Exam Topic 4 Question 32 Discussion:
Question #: 32
Topic #: 4

An output of the Plan Quality Management process is:


A.

A process improvement plan,


B.

Quality control measurements.


C.

Work performance information,


D.

The project management plan.


Get Premium PMI-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.