PMI-001 Exam Topic 3 Question 25 Discussion:
Question #: 25
Topic #: 3

Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?


A.

Project Plan


B.

Responsibility Matrix


C.

Issue Log


D.

Scope Document