PMI Project Management Professional v5 PMI-001 Question # 271 Topic 28 Discussion

PMI Project Management Professional v5 PMI-001 Question # 271 Topic 28 Discussion

PMI-001 Exam Topic 28 Question 271 Discussion:
Question #: 271
Topic #: 28

Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:


A.

Verified deliverables.


B.

Validated deliverables.


C.

Acceptance criteria.


D.

Activity resource requirements.