PMI-001 Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods?


A.

BAC


B.

EAC


C.

ETC


D.

WBS