PMI-001 Exam Topic 19 Question 183 Discussion:
Question #: 183
Topic #: 19

Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?


A.

Cost-reimbursable contracts


B.

Time and Material contracts (T&M)


C.

Fixed-price contracts


D.

Cost Plus Fixed Fee Contracts (CPFF)


Get Premium PMI-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.