PMI Project Management Professional v5 PMI-001 Question # 180 Topic 19 Discussion

PMI Project Management Professional v5 PMI-001 Question # 180 Topic 19 Discussion

PMI-001 Exam Topic 19 Question 180 Discussion:
Question #: 180
Topic #: 19

At the end of the project, what will be the value of SV?


A.

Positive


B.

Zero


C.

Negative


D.

Greater than one