Which is the correct formula for calculating expected activity cost for three-point estimating?


A.

Ce = (C0 + 6Cm + Cp)/4


B.

Ce = (6C0 + Cm + Cp)/4


C.

Ce = (C0 + 4Cm + Cp)/6


D.

Ce = (C0 + C„, + 4Cp) / 6