PMI Project Management Professional v5 PMI-001 Question # 162 Topic 17 Discussion

PMI Project Management Professional v5 PMI-001 Question # 162 Topic 17 Discussion

PMI-001 Exam Topic 17 Question 162 Discussion:
Question #: 162
Topic #: 17

Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?


A.

Product scope description


B.

Procurement statement of work


C.

Project schedule


D.

Work breakdown structure (WBS)


Get Premium PMI-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.