PMI-001 Exam Topic 15 Question 142 Discussion:
Question #: 142
Topic #: 15

Project management processes are:


A.

Static; they must not change across different projects.


B.

Applied globally and across all industry groups.


C.

Discrete elements with well-defined interfaces.


D.

Project phases, applied as required in different projects.


Get Premium PMI-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.