New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional v5 PMI-001 Question # 139 Topic 14 Discussion

PMI Project Management Professional v5 PMI-001 Question # 139 Topic 14 Discussion

PMI-001 Exam Topic 14 Question 139 Discussion:
Question #: 139
Topic #: 14

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?


A.

Control Schedule


B.

Define Activities


C.

Develop Schedule


D.

Estimate Activity Resources


Get Premium PMI-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.