PMI-001 Exam Topic 13 Question 126 Discussion:
Question #: 126
Topic #: 13

Which process should be conducted from the project inception through completion?


A.

Monitor and Control Project Work


B.

Perform Quality Control


C.

Perform Integrated Change Control


D.

Monitor and Control Risks