PMI Project Management Professional v5 PMI-001 Question # 120 Topic 13 Discussion

PMI Project Management Professional v5 PMI-001 Question # 120 Topic 13 Discussion

PMI-001 Exam Topic 13 Question 120 Discussion:
Question #: 120
Topic #: 13

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?


A.

$50


B.

$100


C.

$125


D.

$200


Get Premium PMI-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.