PMI Project Management Professional v5 PMI-001 Question # 118 Topic 12 Discussion

PMI Project Management Professional v5 PMI-001 Question # 118 Topic 12 Discussion

PMI-001 Exam Topic 12 Question 118 Discussion:
Question #: 118
Topic #: 12

A project manager needs to deliver the project 2 weeks before the planned date without changing the scope. Which of the following techniques may be applied to reevaluate the schedule?


A.

What-if scenario analysis


B.

Critical chain method


C.

Schedule crashing


D.

Resource leveling


Get Premium PMI-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.