PMI Project Management Professional v5 PMI-001 Question # 110 Topic 12 Discussion

PMI Project Management Professional v5 PMI-001 Question # 110 Topic 12 Discussion

PMI-001 Exam Topic 12 Question 110 Discussion:
Question #: 110
Topic #: 12

The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:


A.

Earned value management.


B.

Forecasting.


C.

Critical chain methodology.


D.

Critical path methodology.


Get Premium PMI-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.