PMI-001 Exam Topic 10 Question 98 Discussion:
Question #: 98
Topic #: 10

Which of the following includes how requirements activities will be planned, tracked, and reported?


A.

Configuration management plan


B.

Scope baseline


C.

Requirements management plan


D.

Schedule baseline