PMI-001 Exam Topic 10 Question 94 Discussion:
Question #: 94
Topic #: 10

Which of the following is a tool and technique used in the Develop Schedule process?


A.

Three-point estimates


B.

Resource leveling


C.

Precedence diagramming method


D.

Bottom-up estimating


Get Premium PMI-001 Questions