PMI Project Management Professional v5 PMI-001 Question # 92 Topic 10 Discussion

PMI Project Management Professional v5 PMI-001 Question # 92 Topic 10 Discussion

PMI-001 Exam Topic 10 Question 92 Discussion:
Question #: 92
Topic #: 10

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?


A.

0.03


B.

0.06


C.

0.10


D.

0.50