PMI Project Management Professional v5 PMI-001 Question # 7 Topic 1 Discussion

PMI Project Management Professional v5 PMI-001 Question # 7 Topic 1 Discussion

PMI-001 Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:


A.

budget at completion (BAC)


B.

earned value management (EVM)


C.

to-complete performance index


D.

cost performance index