Question #: 102
Topic #: 9

Paula is program manager for her organization. It has come to her attention that several of the projects within her program have stalled which has now caused her project to be delayed. Paula is required by her organization to create a certain type of report when there are variances in the program dealing with time and cost. What type of report is Paula likely to create in this instance?


A.

Earned Value Management report on the schedule performance index


B.

Exceptions report


C.

Status report


D.

Quality Control Report