PgMP Exam Topic 7 Question 83 Discussion:
Question #: 83
Topic #: 7

Robert's program is slipping on its schedule and management has asked that Robert find a method to compress the duration of the program. What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?


A.

Lead time


B.

Crashing


C.

Lag time


D.

Fast tracking