Question #: 49
Topic #: 3

You are the project manager for your organization. Your project team has finished the second phase of a seven-phase project. At the end of each phase, management must review the work your project team has completed and determine if the project should be allowed to continue. What name describes this type of end- of-phase review management is completing on your project?


A.

Quality control


B.

Kill point


C.

Phase review


D.

Audit