PMI Portfolio Management Professional (PfMP) PfMP Question # 40 Topic 5 Discussion

PMI Portfolio Management Professional (PfMP) PfMP Question # 40 Topic 5 Discussion

PfMP Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5

One of your component managers came to you to tell you about a risk affecting his component that will badly impact the component and might affect the portfolio. After assessment, the risk turned out to be of low probability with high impact. What do you do as a portfolio manager?


A.

Inform him to submit a change request to raise the component contingency because of this risk


B.

Inform the component manager to add the risk to the risk register and follow up on it closely


C.

Inform the component manager to add the risk to the risk register, assign a senior risk owner to it in order to follow up on it closely


D.

Inform him that he does not need to worry, you will have a risk contingency reserve for his risk at a portfolio level