PfMP Exam Topic 4 Question 39 Discussion:
Question #: 39
Topic #: 4

Assume the organization's strategy has undergone a significant change, and as a result the mix of components in the portfolio also will change. As the portfolio manager, you need to update your charter in order to reflect:


A.

The new 'to be' vision


B.

Interdependencies between the new components


C.

Risk tolerances


D.

Key stakeholders