PMI Portfolio Management Professional (PfMP) PfMP Question # 6 Topic 1 Discussion

PMI Portfolio Management Professional (PfMP) PfMP Question # 6 Topic 1 Discussion

PfMP Exam Topic 1 Question 6 Discussion:
Question #: 6
Topic #: 1

In a portfolio you have a continuous interaction between the portfolio and its components. The approach is top down when it comes to offering guidelines and approaches and becomes bottom up when the components report status and progress to the portfolio. What is the relation between the portfolio and portfolio components when it comes to defining the performance measures and targets (metrics)?


A.

Portfolio metrics are not related to component metrics, each is used at its own level


B.

Metrics are defined at portfolio level and given as guidelines to components in order to define their own metrics


C.

Portfolio metrics used at the portfolio level are the same used at components level


D.

Metrics are defined at components level and rolled up to the portfolio level