CA0-001 Exam Topic 8 Question 79 Discussion:
Question #: 79
Topic #: 8

The Ishikawa diagram, Pareto chart, control charts, and statistical sampling are examples of ________.


A.

Quality assurance


B.

Quality control


C.

Quality rules


D.

CMM