Question #: 130
Topic #: 14

Scope verification is PRIMARILY concerned with which of the following?


A.

Acceptance of the work deliverables.


B.

Accuracy of the work deliverables.


C.

Approval of the scope statement.


D.

Accuracy of the work breakdown structure.