PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 107 Topic 11 Discussion

PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 107 Topic 11 Discussion

CA0-001 Exam Topic 11 Question 107 Discussion:
Question #: 107
Topic #: 11

A project team is in which of the following processes when they finalize all activities across all of the management process groups to formally complete the project?


A.

Closing


B.

Executing


C.

Monitoring and Controlling


D.

Planning