PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 103 Topic 11 Discussion

PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 103 Topic 11 Discussion

CA0-001 Exam Topic 11 Question 103 Discussion:
Question #: 103
Topic #: 11

If a project with a SPI of 1.8, what you tell?


A.

The project is running ahead of the schedule


B.

The project is running behind of the schedule


C.

Resources assigned to the project cost 1.8 units


D.

None