Comprehensive and Detailed Explanation From Exact Extract:
One of the key drivers for initiating a programme rather than a project is when the organization requires a shift in culture, behavior, and working practices to achieve strategic objectives.
MSP Foundation, 5th Edition explains:
“Organizations often use programmes when there is a need to change the prevailing culture, ways of working, or strategic positioning.”
Therefore, option B is correct.
—