Comprehensive and Detailed Explanation From Exact Extract:
Within MSP, a risk owner is appointed to manage specific programme risks. Their actions and responses are overseen by theProgramme Board, which evaluates whether the responses sufficiently address identified threats or opportunities in line with the overall programme approach. This is confirmed by guidance on risk governance in MSP:
Thus,Cis correct.