As a Pega Business Architect, with which three stakeholders do you collaborate to manage scope, timeline, and budget? (Choose Three)
Project Delivery Lead
Scrum Master
Product Owner
System Architect
Business Analyst
Comprehensive and Detailed Explanation From Exact Extract:
This question tests stakeholder collaboration.
A: Correct. Leads manage project constraints.Extract: Pega Academy,Project Management: “Project Delivery Leads oversee scope and budget.”
B: Correct. Scrum Masters manage timelines.Extract: Pega Academy,Agile Delivery: “Scrum Masters ensure timeline adherence.”
C: Correct. Product Owners define scope.Extract: Pega Academy,Agile Delivery: “Product Owners prioritize scope.”
D: Incorrect. SAs implement, not manage.Extract: Pega Academy,Agile Delivery: “System Architects build solutions.”