Pegasystems Certified Pega Business Architect 24 PEGACPBA24V1 Question # 31 Topic 4 Discussion

Pegasystems Certified Pega Business Architect 24 PEGACPBA24V1 Question # 31 Topic 4 Discussion

PEGACPBA24V1 Exam Topic 4 Question 31 Discussion:
Question #: 31
Topic #: 4

Which project nears the end of the Prepare phase, you prepare the project plan for review with your development team, two elements does the project plan include? (Choose Two)


A.

Governance structure


B.

Epic and user stories


C.

RAID log (Risks, Actions, Issues, and Decisions)


D.

Definition of Ready (DoR)


E.

Project team resourcing’s