The PDCA cycle (Plan-Do-Check-Act) is a core framework in ISO 45001 for continual improvement of the OH&S management system. An Environmental Management Program is part of ISO 14001 (Environmental Management System) and not ISO 45001.
Analysis of Options:
A. Treatment of Risks:Correct. Risk treatment is part of the Plan phase.
B. OHSMS Policy:Correct. The policy is developed in the Plan phase.
C. Environment Management Program:Incorrect. This is outside the scope of ISO 45001 and relates to ISO 14001.
D. Analyzing OHSMS Performance:Correct. Performance analysis is part of the Check phase.
ISO References:
Clause 0.3: PDCA framework in ISO 45001.