The plan phase in the PDCA cycle establishes the operating framework for the BCMS by defining the scope, objectives, policy, and processes of the BCMS. The plan phase also involves conducting a business impact analysis (BIA) and a risk assessment (RA) to identify the business continuity requirements and strategies. The plan phase is one of the key requirements of ISO 22301, as it provides the foundation and direction for the BCMS implementation and improvement. References: ISO 22301 Auditing eBook, page 10 1; ISO 22301:2019, clause 0.3 2