Question #: 1
Topic #: 1

You are providing oversight for the delivery of a new Exadata Database Machine.

1. Stabilize the Exadata Rack.

2. Unpack Oracle Exadata Rack.

3. Review the safety guidelines.

4. Let the Exadata acclimatize for 24 hours.

5. Power on Exadata PDU A.

6. Place Exadata in its allocated space.

7. Power on Exadata PDU B.

What is the correct order of these steps?


A.

4,3,2,6,1,7,5


B.

3,2,6,4,1,7,5


C.

2,3,4,6,1,7,5


D.

3,2,6,1,4,7,5


E.

2,6,1,4,3,7,5