Oracle E-Business Suite R12 Project Essentials Exam 1z0-511 Question # 10 Topic 2 Discussion

Oracle E-Business Suite R12 Project Essentials Exam 1z0-511 Question # 10 Topic 2 Discussion

1z0-511 Exam Topic 2 Question 10 Discussion:
Question #: 10
Topic #: 2

A contractor is engaged to carry out a statement of work by a customer. The contract is fixed price, and milestone payments will be made based on the individual completion of agreed deliverables. The contract specifies that 10% of any invoice totals must be withheld. The exception to this rule is that if certain deliverables are met ahead of the agreed schedule, then the full amount can be invoiced. How would this scenario be set up in Oracle Projects?


A.

CustomerRetention Billing is implemented with a Withholding Term ofExpenditure Category.


B.

10% ofproject costs isset with abilling hold (as required) inExpenditureInquiry.


C.

A taskis used to collectcosts that are to be withholdingand the task is set to non-billable asrequired.


D.

CustomerRetention Billing isimplemented with aWithholding Term based onEvent Types.


E.

A customerbill splitisimplemented to send 10% ofall invoiced costs to a dummy customer.