The Project Cost to Accounting process manages indirect costs via:
Burdening (B):Aggregates raw and indirect (burden) costs for a total cost view.
Allocation (C):Distributes costs (including indirect) to projects, ensuring accurate assignment.
Calculation Manager (A):Transfers balances, not specific to indirect costs.
[Reference:Oracle Fusion Cloud ERP Foundations Training – Project Cost to Accounting, ]