Which two capabilities of the Project Cost to Accounting process help in managing the indirect cost on projects?


A.

Calculation Manager helps transfer balances from a source account to target accounts


B.

Burdening provides the aggregate of raw and burden costs to represent the total cost of doing business accurately


C.

Allocation helps distribute actual amounts from project sources, ledger sources, or fixed amounts to target projects


D.

Capital Events helps group assets and costs on a project