Oracle Manufacturing Cloud 2025 Implementation Professional 1z0-1075-25 Question # 8 Topic 1 Discussion

Oracle Manufacturing Cloud 2025 Implementation Professional 1z0-1075-25 Question # 8 Topic 1 Discussion

1z0-1075-25 Exam Topic 1 Question 8 Discussion:
Question #: 8
Topic #: 1

A manufacturing plant works in two shifts of eight hours each. A Manufacturing user wants four units of a work center resource, R1, to be available during nonworking time, outside the regular shift on a particular day.

Which is the correct sequence of steps to create a resource exception on the Manage Work Center Resource Calendar page?


A.

Click Inside the existing shift time on a specific date > Go to the Create Work Center page > Click the Resource Availability tab > Click the Add icon > Select R1 from the Resource dropdown list > Enter 4 in Default Units Available.


B.

Click inside the existing shift time on a specific date > Go to the Actions menu > Select Create Resource Exception > Populate the Start and Duration Fields > Go to the Resource Availability region > Populate A units in the Default Availability column.


C.

Click outside the existing shift time on a specific date > Go to the Actions menu > Select Create Resource Exception > Populate the Start and Duration fields > Go to the Resource Availability and Overrides region > Populate 4 units in the Availability Override column.


D.

Click outside the existing shift time on a specific date > Go to the Create Work Center page > Click the Resource Availability tab > Click the Add icon > Select R1 from the Resource drop-