Oracle Manufacturing Cloud 2025 Implementation Professional 1z0-1075-25 Question # 7 Topic 1 Discussion

Oracle Manufacturing Cloud 2025 Implementation Professional 1z0-1075-25 Question # 7 Topic 1 Discussion

1z0-1075-25 Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

A manufacturing plant has two shifts of eight hours each for the work center WCI: day shift and night shift. You associate four units each of the resources R1, R2, R3, and R4 to WCI. The customer wants to assign ail units of R2 available for day and night shift.

What is the correct sequence of steps to achieve this?


A.

Associate R2 with WC1 > Select the Available 24 Hours check box > Go to the Resource Availability region > Enter 4 in the Day Shift column > Enter 4 In the Night Shift column.


B.

Associate R2 with WC1 > Deselect the Available 24 Hours check box > Go to the Resource Availability region > Enter 4 in the Day Shift column > Enter 4 In the Night Shift column.


C.

Associate R2 with WCI > Select the Available 24 Hours check box > Go to the Resource Availability region > Enter 2 in the Day Shift column > Enter 2 in the Night Shift column.


D.

Associate R2 with WCI > Deselect the Available 24 Hours check box > Go to the Resource Availability region > Enter 2 In the Day Shift column > Enter 2 In the Night Shift column.