Oracle Manufacturing Cloud 2024 Implementation Professional 1z0-1075-24 Question # 8 Topic 1 Discussion

Oracle Manufacturing Cloud 2024 Implementation Professional 1z0-1075-24 Question # 8 Topic 1 Discussion

1z0-1075-24 Exam Topic 1 Question 8 Discussion:
Question #: 8
Topic #: 1

During a Manufacturing Cloud implementation, a Production Supervisor wants to close the work orders for the previous month and make sure that they include the correct cost.

What must they do to achieve this?


A.

Exclude cost variances while closing last month's work orders because those can be applied directly In Subledger Accounting.


B.

Make sure that all costs are Included while closing last month's work orders; however, variances can be Included after closing the work orders.


C.

Include all costs and variances in last month's work orders and close them; however, the work orders where updates are expected must not be closed.


D.

Update work order costs at any time; they can be updated regardless of the status of the workorder