Oracle Project Management Cloud 2024 Implementation Professional 1z0-1057-24 Question # 33 Topic 4 Discussion

Note! The 1z0-1057-24 Exam is no longer available. Get in touch with our Live Chat or email us for more information about the 1z0-1057-25 Exam.

Oracle Project Management Cloud 2024 Implementation Professional 1z0-1057-24 Question # 33 Topic 4 Discussion

1z0-1057-24 Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

When scheduling the Update Project Performance Data process to run on a periodic basis, which summarization method would you select? (Choose the best answer.)


A.

Bulk


B.

Detail


C.

Incremental


D.

Summary


Get Premium 1z0-1057-24 Questions

Contribute your Thoughts:


Chosen Answer: