As an HR specialist, you have been asked to create and assign a new schedule to employees that will be working in a new shift. Which steps should you perform to achieve this?
A.
Create a shift, create a work pattern, create a work schedule, and assign the shift through the Manage Employment task.
B.
Create a shift, create a work pattern, create a work schedule, and assign the schedule through work schedule assignment.
C.
Create a shift, create a work pattern, and assign the work pattern through work scheduleassignment.
D.
Create a work pattern, create a shift, create a work schedule, and assign the schedule through work schedule assignment.
To create and assign a new schedule in Oracle HCM Cloud, follow these steps per the documentation:
Create a Shift: Define the shift (e.g., hours) in Manage Shifts.
Create a Work Pattern: Combine shifts into a pattern (e.g., weekly rotation) in Manage Work Patterns.
Create a Work Schedule: Build the schedule using the pattern in Manage Work Schedules.
Assign the Schedule: Use the "Work Schedule Assignment" task (not Manage Employment directly) to assign the schedule to employees’ assignments.
Option A incorrectly assigns the shift via Manage Employment, which handles assignment details, not schedule assignment. Option C skips creating a work schedule, which is required. Option D reverses the logical order (pattern before shift). Option B accurately reflects the sequence and uses the correct "Work Schedule Assignment" task for assignment.
[References: Oracle Docs - "Using Global Human Resources" (docs.oracle.com, published 2023-10-03), Work Schedules section., , ]
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit